Posted on: October 7, 2019

Utility Work on Pioneer Road

We Energies Electric is planning on beginning its relocations during the week of October 7th and anticipates their work to take approximately four (4) weeks. When We Energies Electric work is complete, AT&T and Charter Communications will conduct their relocations. We Energies Gas anticipates to begin their work at the end of October. 

Please be conscious of the utility crews doing work in the area over the next few months. Traffic may be controlled by flaggers at time which could result in travel delays. For more information, please see the link below or call the County Highway Department directly at (262)-335-4435. 