2019 Village Highway Improvement Construction to Begin Monday, May 20th

Construction for the 2019 Highway Improvement Program will begin Monday, May 20th. Significant completion of all 5 miles of road projects is planned for the week of June 17th. Please note all dates are weather dependent. Additionally, these construction zones will be accessible to local traffic only. Those who do not reside within the project limits will be directed to use alternative roads. 

Roads to be Reconstructed in 2019:
Hubertus Road:
from Friess Lake Road to Plat Road
Wooded Ridge Subdivision Roads:
Wooded Ridge Trail, Mitchell Trail, Amber Court, Amber Trail, Royal Oak Court, Northwood Trail, and Oak Ridge Court
Reflections Village Subdivision:
Reflections Drive, Cambridge Drive, and Cambridge Lane
Monches Road:
from Hillside Road to Scenic Road
Scenic Road:
from CTH Q to Willow Creek Road

Timeline for Construction: 
Construction timelines will vary from each project location. Below are the begin dates for work, and the anticipated time to complete each project. At times most or all projects will be taking place at the same time. To see a full map of work to be completed, please click here

Hubertus Road:
Work begins May 27th, completion estimated in two (2) weeks.
Wooded Ridge Subdivision:
Work begins May 20th, completion estimated in one (1) month. 
Reflections Village Subdivision:
Work begins May 20th, completion estimated in two (2) weeks. 
Monches Road and Scenic Road:
Work begins May 20th, completion estimated in one (1) month.

To view each road project's timeline, please click here