Current Construction / Road Closures

10th Annual Spring Preconstruction Meetings - Canceled due to COVID-19

Out of concern for COVID-19, the Village will not hold its 10th Annual Spring Pre-Construction meetings. Instead, impacted property owners are encouraged to contact Public Works Supervisor Brett Thicke via email at DPW@richfieldwi.gov for questions, comments, and concerns. During the week of March 30th, property owners were notified directly of the upcoming construction and anticipated timelines. Business owners were also contacted via a separate mailer. Construction is anticipated to start the second week of June and is scheduled to be completed by the end of July. It is important to note that these timelines are weather dependent and are only a reasonable estimation of the time it will take to construct these roads. As a part of the construction, we work to notify our community partners like the U.S. Post Office, local bus companies, the waste haulers who service our community, and private parcel delivery to mitigate any potential service inconveniences that may arise from construction. While the roads will always be accessible to through traffic, there may be times where motorists will be inconvenienced for the safety of the workers. 

Investment

Our 2020 Highway Improvement Program is the single largest budgeted item in the Village and the Department of Public Works accounts for approximately 52% of our Village budget. Therefore, Village Board and Staff strive to continue to involve residents, receive input, and keep an open dialogue with property owners; especially when it comes to road construction.

Roads to be Reconstructed in 2020:

Hubertus Road from Hillside Road to Scenic Road

Hubertus Road from Scenic Road to Mayfield Road 

Elmwood Road from STH 164 to Hillside Road

Kreuser’s Ridge 

Jencris Court 

Timeline for Construction:

Construction timelines will vary from each project location. Below are the begin dates for work, and the anticipated time to complete each project. 

Hubertus Road from Hillside Road to Mayfield Road - June 15th through July 17th 

Elmwood Road from STH 164 to Hillside Road - Jun 18th through July 20th 

Jencris Court - June 22nd through July 16th

Kreuser’s Ridge - June 24th through July 29th 

Public Documents

2020.3.30 Letter to Property Owners (General Example Copy)

Proposed Timeline from March 31st Pre-Construction Meeting with Village Engineer and Contractor